Land Clearing Permit Requirements by State: 2026 Reference

Ocala Land Clearing Research is the independent research and reference section of ocalalandclearing.net. This is a permit-routing reference, not legal advice. A site-specific determination belongs with the responsible agency or a qualified professional.

51Jurisdictions — 50 states and the District of Columbia
19★ Directly verified — state-specific rule or overlay read against a primary government source
32● Routing rows — NPDES authority verified from EPA; state permit pending direct re-verification
4Jurisdictions where EPA (not the state) issues NPDES permits: MA, NH, NM, DC

What is the federal construction stormwater baseline for land clearing?

EPA's Construction General Permit covers stormwater discharges from construction sites that disturb one acre or more, and smaller sites that are part of a larger common plan of development or sale that will ultimately disturb one acre or more. This is the federal floor — most states run their own authorized NPDES programs and may set requirements that are broader or stricter.

Four jurisdictions in this dataset have EPA issue NPDES permits directly rather than the state: Massachusetts (EPA Region 1), New Hampshire (EPA Region 1), New Mexico (EPA Region 6), and the District of Columbia (EPA Region 3). Each still has state-level land-disturbance, erosion, wetland, and burn rules that operate separately from NPDES.

A one-acre screen is not a universal permission to clear less than one acre without a permit. State erosion and sediment control programs, local grading ordinances, wetland and waterway rules, forest-practice notification requirements, and burn authorizations can each apply independently — sometimes at disturbance areas far below one acre. Maryland and Pennsylvania, for example, both trigger an erosion and sediment control plan requirement at 5,000 square feet.

For Ocala and Marion County specifically, see the local permit guide. For land clearing scope and service comparisons, see the services overview.


What do the verification tiers mean?

Directly verified. The summarized state-specific rule or official program page was read directly against a primary government source and is stood behind as of .
Routing row. The NPDES authority and official program starting point were compiled from U.S. EPA primary sources. The current state-specific construction permit has not received a full row-level re-verification for version 1.0. Use the linked official program page as the starting point.

Rows marked ● correctly identify the NPDES issuer and the official starting page, but do not assert a specific state threshold. Read the current state permit and local code before publishing or acting on a definitive threshold for those jurisdictions.

For the site's sourcing and correction standards, see editorial and source standards.


Land clearing permit authority by state — all 51 jurisdictions

Each row links to the official program page. The "Key overlay or routing note" column summarizes the verified state rule for ★ rows; for ● rows it confirms the routing starting point and notes that the state-specific permit threshold is pending re-verification.

Table 1
Land clearing permit authority and state overlay — 51 jurisdictions, verified July 23, 2026
StateCodeTierNPDES authorityOfficial programKey overlay or routing note
AlabamaALState-authorizedAlabama Department of Environmental ManagementCoverage required at 1 acre or more, or for a smaller site in a common plan totaling 1 acre or more, or for a site of any size whose discharge may cause or contribute to a water-quality concern. Normal agricultural and silvicultural activities listed as exclusions, subject to program terms.
AlaskaAKState-authorizedAlaska Department of Environmental ConservationUse Alaska's APDES construction-stormwater program for the 1-acre/common-plan screen. Qualifying operations on forest land separately subject to a forest-practice notification received by the state forester at least 30 days before the operation, subject to stated exceptions.
ArizonaAZState-authorizedArizona Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
ArkansasARState-authorizedArkansas Division of Environmental QualityCurrent permit separates large sites (5 acres or more) from small sites (1 to less than 5 acres); small sites receive automatic coverage after required on-site documents are posted. Current permit expires October 31, 2026; renewal listed as effective November 1, 2026.
CaliforniaCAState-authorizedCalifornia State Water Resources Control BoardState construction-stormwater program for development disturbance. Commercial timber harvesting on nonfederal land separately regulated through CAL FIRE's CalTREES system; timber-harvest plans prepared by Registered Professional Foresters.
ColoradoCOState-authorizedColorado Department of Public Health and EnvironmentNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
ConnecticutCTState-authorizedConnecticut Dept. of Energy and Environmental ProtectionNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
DelawareDEState-authorizedDelaware Dept. of Natural Resources and Environmental ControlStatewide sediment-and-stormwater system covers projects disturbing more than 5,000 square feet, with project-type exemptions and special pathways in Chapter 40. NPDES construction-stormwater coverage separately uses the 1-acre/common-plan screen.
District of ColumbiaDCEPA-issued NPDESlocal DOEE erosion/stormwater rulesU.S. EPA Region 3 / District Dept. of Energy and EnvironmentEPA, not DC, issues NPDES permits. E&SC plan generally required except for activities disturbing less than 50 square feet. District guidance identifies 5,000 square feet as the major land-disturbance threshold for a stormwater management plan. DOEE administers separate local erosion and stormwater requirements.
FloridaFLState-authorizedFlorida Department of Environmental ProtectionCGP coverage required when activity disturbs at least 1 acre (or less than 1 in a common plan) and discharges stormwater to state surface waters or an MS4. Florida DEP's State 404 program remains paused as of July 23, 2026; USACE is current Section 404 permitting authority.
GeorgiaGAState-authorizedGeorgia Environmental Protection DivisionNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
HawaiiHIState-authorizedHawaii Department of Health, Clean Water BranchNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
IdahoIDState-authorizedIdaho Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
IllinoisILState-authorizedIllinois Environmental Protection AgencyNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
IndianaINState-authorizedIndiana Department of Environmental ManagementNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
IowaIAState-authorizedIowa Department of Natural ResourcesNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
KansasKSState-authorizedKansas Department of Health and EnvironmentNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
KentuckyKYState-authorizedKentucky Division of WaterKYR10 construction permit (effective January 3, 2025 through December 31, 2029) covers disturbance of 1 acre or more and smaller activity in a larger common plan totaling 1 acre or more.
LouisianaLAState-authorizedLouisiana Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
MaineMEState-authorizedMaine Department of Environmental ProtectionNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
MarylandMDState-authorizedMaryland Department of the EnvironmentApproved erosion and sediment control plan required for earth moving that disturbs 5,000 square feet or more or moves 100 cubic yards or more of soil. Local delegated programs may be stricter. Construction-stormwater NPDES is a separate screen.
MassachusettsMAEPA-issued NPDESU.S. EPA Region 1EPA, not Massachusetts, issues NPDES permits. NPDES authority and program route verified from EPA. State-specific threshold pending re-verification.
MichiganMIState-authorizedMichigan Dept. of Environment, Great Lakes, and EnergySoil erosion and sedimentation control permit and plan required for earth changes disturbing 1 acre or more, or located within 500 feet of the water's edge of a lake or stream. Local enforcing agency or county may administer the Part 91 permit.
MinnesotaMNState-authorizedMinnesota Pollution Control AgencyNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
MississippiMSState-authorizedMississippi Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
MissouriMOState-authorizedMissouri Department of Natural ResourcesNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
MontanaMTState-authorizedMontana Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
NebraskaNEState-authorizedNebraska Department of Environment and EnergyNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
NevadaNVState-authorizedNevada Division of Environmental ProtectionNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
New HampshireNHEPA-issued NPDESU.S. EPA Region 1 / NH Dept. of Environmental ServicesEPA, not New Hampshire, issues NPDES permits. State Alteration of Terrain program can require a permit when cumulative earth disturbance exceeds 100,000 square feet, or 50,000 square feet within protected shoreland, subject to program definitions and exemptions.
New JerseyNJState-authorizedNew Jersey Department of Environmental ProtectionSoil Erosion and Sediment Control Act generally requires a certified plan for covered non-agricultural clearing, grading, or construction disturbing more than 5,000 square feet. Separate NJDEP construction-stormwater requirements may apply at the 1-acre/common-plan level.
New MexicoNMEPA-issued NPDESU.S. EPA Region 6 / New Mexico Environment DepartmentEPA, not New Mexico, issues NPDES permits. NPDES authority and program route verified from EPA. State-specific threshold pending re-verification.
New YorkNYState-authorizedNew York State Dept. of Environmental ConservationNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
North CarolinaNCState-authorizedNorth Carolina Department of Environmental QualityErosion and sedimentation control plan required to be submitted at least 30 days before land disturbance begins on a site involving over 1 acre, and approved before land-disturbing activity starts. Delegated local programs may be the reviewing authority.
North DakotaNDState-authorizedNorth Dakota Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
OhioOHState-authorizedOhio Environmental Protection AgencyNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
OklahomaOKState-authorizedOklahoma Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
OregonORState-authorizedOregon Department of Environmental QualityState construction-stormwater program for development disturbance. For forestry work on nonfederal land, the responsible person must file an E-Notification or a permit at least 15 days before the operation.
PennsylvaniaPAState-authorizedPennsylvania Department of Environmental ProtectionWritten erosion and sediment control plan required when total earth disturbance is 5,000 square feet or more, when another rule requires it, or when proximity to drainage may discharge to High Quality or Exceptional Value waters. County conservation districts often administer review.
Rhode IslandRIState-authorizedRhode Island Department of Environmental ManagementMultiple independent triggers: specified freshwater-wetland conditions, certain work involving more than 10,000 square feet of existing impervious cover, fill in a floodplain, alteration of flow to waters, or stormwater discharge from disturbance above 1 acre/common-plan thresholds.
South CarolinaSCState-authorizedSouth Carolina Dept. of Environmental ServicesNPDES coverage at 1 acre/common-plan threshold. In non-coastal counties, projects disturbing less than 1 acre must generally submit a notification for an exemption determination; coastal projects have separate routing. 2026 CGP issued February 27, 2026.
South DakotaSDState-authorizedSouth Dakota Dept. of Agriculture and Natural ResourcesNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
TennesseeTNState-authorizedTennessee Department of Environment and ConservationNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
TexasTXState-authorizedTexas Commission on Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
UtahUTState-authorizedUtah Division of Water QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
VermontVTState-authorizedVermont Department of Environmental ConservationNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
VirginiaVAState-authorizedVirginia DEQ / local VESMP authorityLocal erosion/stormwater programs generally regulate land disturbance at 10,000 square feet, or 2,500 square feet in a Chesapeake Bay Preservation Area. Statewide construction-stormwater screen remains 1 acre/common plan; localities may adopt lower thresholds.
WashingtonWAState-authorizedWashington State Department of EcologyConstruction stormwater through Washington Ecology. Timber harvesting and related forest-practice activities separately routed through Washington DNR's Forest Practices Application/Notification process.
West VirginiaWVState-authorizedWest Virginia Department of Environmental ProtectionNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
WisconsinWIState-authorizedWisconsin Department of Natural ResourcesNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.
WyomingWYState-authorizedWyoming Department of Environmental QualityNPDES authority and official program starting point verified from EPA. State-specific construction permit threshold pending direct source re-verification in dataset v1.0.

Source: Ocala Land Clearing Research. NPDES authority compiled from U.S. EPA, NPDES State Program Authority page. State-specific rules for ★ rows read directly against the linked primary government source. All rows verified .


What are the directly verified state-level overlays?

The 19 jurisdictions marked ★ were read directly against a primary government source. Several have disturbance thresholds well below the federal one-acre baseline. The table below summarizes the verified threshold or overlay for each, with the primary source linked.

Table 2
Directly verified (★) state overlays — thresholds, additional layers, and primary sources
StateVerified threshold or overlayAdditional checks notedPrimary source
AL Alabama1 acre or more; or smaller in common plan; or any size with potential water-quality concern. Agricultural and silvicultural exclusions per program terms.Also check wetlands/streams, local grading or tree rules, and debris-burning authorization.ADEM — Do I Need Permit Coverage?
AK AlaskaAPDES for 1-acre/common-plan screen. Qualifying forest-land operations: notification to state forester ≥30 days before operation, subject to stated exceptions.Forest-operation rules are distinct from construction stormwater and local development approvals.Alaska Forest Resources and Practices Regulations (11 AAC 95.030)
AR ArkansasLarge sites (5 acres or more) vs. small sites (1 to less than 5 acres); small sites receive automatic coverage after required on-site documents are posted. Current permit expires October 31, 2026; renewal effective November 1, 2026.Re-check the November 1, 2026 renewal before relying on post-renewal procedures.Arkansas DEQ — General Stormwater Permits
CA CaliforniaState construction-stormwater program for development disturbance. Commercial timber harvesting on nonfederal land separately regulated through CAL FIRE CalTREES; plans prepared by Registered Professional Foresters.A timber-harvest approval is not a substitute for wetlands, grading, county, fire, or construction-stormwater review.CAL FIRE — CalTREES
DE Delaware>5,000 sq ft triggers the statewide sediment-and-stormwater system, with project-type exemptions and special pathways in Chapter 40. NPDES construction-stormwater coverage separately uses the 1-acre/common-plan screen.Read current Delaware Code, current DNREC regulations, and the delegated plan-review agency's procedures.Delaware Code, Title 7, Chapter 40
DC Dist. of ColumbiaE&SC plan generally required; activities disturbing <50 sq ft exempt. District guidance identifies 5,000 sq ft as the major land-disturbance threshold for a stormwater management plan. EPA (not DC) issues NPDES permits.DOEE administers separate local erosion and stormwater requirements independent of EPA's NPDES program.21 DCMR Chapter 5
FL FloridaCGP coverage required when activity disturbs ≥1 acre (or <1 in a common plan) and discharges stormwater to state surface waters or an MS4. Florida DEP's State 404 program remains paused as of July 23, 2026; USACE is current Section 404 permitting authority.Florida's CGP is separate from an Environmental Resource Permit and local stormwater, tree, grading, right-of-way, or burn requirements. Marion County publishes a tree-removal permit application.Florida DEP — Construction Activity
KY KentuckyKYR10 construction permit (effective through ) covers disturbance of 1 acre or more and smaller activity in a common plan totaling 1 acre or more.Local erosion, grading, wetlands, stream-crossing, and burn requirements remain separate.Kentucky Division of Water — KYR10 Permit Page
MD MarylandApproved erosion and sediment control plan required for earth moving that disturbs 5,000 square feet or more or moves 100 cubic yards or more of soil. Local delegated programs may be stricter.Confirm the delegated county or municipal reviewing authority. NPDES construction-stormwater is a separate screen.Maryland MDE — Soil Erosion and Sediment Control
MI MichiganSESC permit and plan required for earth changes disturbing 1 acre or more, or located within 500 feet of the water's edge of a lake or stream.Local enforcing agency or county may administer the Part 91 permit.Michigan EGLE — SESC Training Manual
NC North CarolinaErosion and sedimentation control plan required to be submitted at least 30 days before land disturbance begins on a site involving over 1 acre, and approved before land-disturbing activity starts.Delegated local programs may be the reviewing authority. Source uses "over one acre" — common-plan and construction-stormwater requirements must also be checked.NC DEQ — Erosion and Sediment FAQs
NH New HampshireEPA (not NH) issues NPDES permits. State Alteration of Terrain program can require a permit when cumulative earth disturbance exceeds 100,000 sq ft, or 50,000 sq ft within protected shoreland, subject to definitions and exemptions.EPA construction-stormwater coverage and local approvals are separate screens.New Hampshire DES — Alteration of Terrain
NJ New JerseySoil Erosion and Sediment Control Act generally requires a certified plan for covered non-agricultural clearing, grading, or construction disturbing more than 5,000 square feet. Separate NJDEP construction-stormwater requirements may apply at 1 acre/common-plan.Check the local Soil Conservation District, current NJDEP construction-stormwater authorization, municipal approvals, and wetlands or flood-hazard permits.NJ Dept. of Agriculture — Soil Erosion and Sediment Control Program
OR OregonState construction-stormwater program for development disturbance. For forestry work on nonfederal land, the responsible person must file an E-Notification or a permit at least 15 days before the operation.Forest-practice filings are separate from construction stormwater, wetlands, local land use, and burning rules.Oregon Dept. of Forestry — E-Notification
PA PennsylvaniaWritten E&SC plan required when total earth disturbance is 5,000 square feet or more, when another rule requires it, or when proximity to drainage may discharge to High Quality or Exceptional Value waters. BMP obligations can apply below 5,000 sq ft.NPDES permit is a separate question; county conservation districts often administer review.Pennsylvania Code, 25 Pa. Code §102.4
RI Rhode IslandMultiple independent triggers: specified freshwater-wetland conditions; work involving more than 10,000 sq ft of existing impervious cover; fill in a floodplain; alteration of flow to waters; or stormwater discharge above 1 acre/common-plan thresholds.Parcel conditions can control applicability even when total disturbance is below one acre.Rhode Island DEM — Stormwater Construction Permitting
SC South CarolinaNPDES coverage at 1 acre/common-plan threshold. In non-coastal counties, projects disturbing less than 1 acre must generally submit a notification for an exemption determination; coastal projects have separate routing and automatic-coverage conditions. 2026 CGP issued .MS4/local approval may also be required.South Carolina DES — Less Than 1 Acre
VA VirginiaLocal VESMP programs generally regulate land disturbance at 10,000 square feet, or 2,500 square feet in a Chesapeake Bay Preservation Area. Statewide construction-stormwater screen remains 1 acre/common plan; localities may adopt lower thresholds.Wetland or stream disturbance can separately require Virginia Water Protection and federal authorization.Code of Virginia — VESMA Act
WA WashingtonConstruction stormwater through Washington Ecology. Timber harvesting and related forest-practice activities separately routed through Washington DNR's Forest Practices Application/Notification process.Forest-practice classification and application type must be determined from current DNR rules and instructions.Washington DNR — Forest Practices Application

Source: Ocala Land Clearing Research. Each ★ row was read directly against the linked primary government source on . Threshold values in bold are stated thresholds; they do not represent a universal yes/no for every project type — exemptions, delegated programs, and project-type conditions all apply.

Verified state disturbance thresholds — quick reference

These are the specific area thresholds confirmed in ★ rows. They do not describe the full permit requirement — exemptions, project types, delegated authorities, and other conditions apply.

Table 3
Verified disturbance thresholds — ★ states only
StateProgramVerified thresholdNotes
DelawareStatewide sediment-and-stormwater (Title 7, Ch. 40)>5,000 sq ftProject-type exemptions apply. NPDES 1-acre screen is separate.
District of ColumbiaLocal E&SC requirement<50 sq ft exempt; 5,000 sq ft major disturbanceEPA (not DC) issues NPDES. DOEE administers local E&SC rules.
MarylandErosion and sediment control plan (MDE)≥5,000 sq ft or ≥100 cubic yardsLocal delegated programs may be stricter.
MichiganPart 91 SESC permit (EGLE)≥1 acre or within 500 ft of waterLocal enforcing agency or county may administer.
New HampshireAlteration of Terrain (NH DES)>100,000 sq ft cumulative; >50,000 sq ft in protected shorelandSeparate from EPA NPDES; subject to program definitions and exemptions.
New JerseySoil Erosion and Sediment Control Act>5,000 sq ft (non-agricultural)Local Soil Conservation District administers. NJDEP stormwater is a separate screen.
North CarolinaErosion and sedimentation control plan (NC DEQ)>1 acrePlan submitted ≥30 days before disturbance; approved before work starts.
PennsylvaniaErosion and sediment control plan (25 Pa. Code §102.4)≥5,000 sq ftAlso triggered by rule requirement or proximity to HQ/EV waters.
Rhode IslandMultiple triggers (RI DEM)>10,000 sq ft impervious; freshwater-wetland conditions; floodplain fill; or ≥1 acre stormwaterTrigger-based; parcel conditions can control independently of disturbance area.
VirginiaLocal VESMP programs10,000 sq ft; 2,500 sq ft in Chesapeake Bay Preservation AreaLocalities may adopt lower thresholds. Statewide 1-acre/common-plan applies for NPDES.

Source: Ocala Land Clearing Research compilation from the primary sources listed in Table 2. Thresholds are as verified on and subject to legislative, regulatory, and program changes.


Which permit screens apply beyond construction stormwater?

The construction stormwater permit is one layer. Land clearing can independently trigger each of the following depending on the project, parcel, and jurisdiction.

  • Local grading and land-disturbance ordinances. Many municipalities and counties require a grading permit for any disturbance above a locally set threshold, often lower than any state stormwater trigger.
  • Local tree-removal or canopy ordinances. Cities and counties often regulate the removal of trees above a set diameter, protected species, or trees within a designated zone. These rules apply regardless of total disturbance area.
  • Federal Section 404 of the Clean Water Act. Discharges of dredged or fill material into waters of the United States — including wetlands — generally require authorization from the U.S. Army Corps of Engineers, or from a state with an EPA-approved Section 404 program, unless an exemption applies. Certain farming and silviculture activities may be exempt subject to the recapture provision.
  • State wetland and waterway permits. States often have independent programs covering activities in or near wetlands, streams, floodplains, or other regulated waters, separate from federal Section 404.
  • State forest-practice notifications or permits. Alaska, California, Oregon, and Washington are all directly verified in this dataset as having separate forest-practice filing requirements for timber harvest or forestry operations on nonfederal land.
  • Debris-burning authorization. Open burning of land-clearing debris is regulated separately by state or local fire authorities. In Florida, land-clearing burns require Florida Forest Service authorization before burning begins.
  • Protected-resource, conservation-easement, and floodplain rules. Listed species, conservation easements, and floodplain designations can each independently require review or authorization.

None of these screens disappears because total disturbance is below one acre or because the construction stormwater permit is not triggered.


What are the specific permit layers for Florida and Marion County?

Florida's row in this dataset is directly verified (★). The verified facts:

  • Florida DEP's construction-stormwater CGP is required when activity disturbs at least 1 acre (or less than 1 in a common plan) and discharges stormwater to state surface waters or an MS4.
  • Florida DEP's State 404 program remains paused as of ; the U.S. Army Corps of Engineers is the current Section 404 permitting authority.
  • Marion County publishes a tree-removal permit application, requires right-of-way authorization for clearing in public right-of-way, and routes qualifying large land-clearing burns through Florida's forestry burn-authorization system.
  • Marion County states that tree trimming and removal service providers are not required by the State of Florida or Marion County to be licensed before performing those services. That statement does not resolve permits, development approvals, environmental authorizations, or licensing for related trades.

The dedicated Ocala and Marion County guide covers these layers in more detail and includes the responsible agency contacts:

Ocala and Marion County Land-Clearing Permit Guide →

For context on Florida land-clearing costs and FDOT public bid data, see the land clearing cost per acre research page.


What are the limitations of this reference?

This dataset is a permit-routing reference. It does not determine whether a permit is required for a particular parcel.

  • Rules can change. Permit renewal, legislation, agency reorganization, local ordinance, and litigation can all change requirements between verifications. The last-verified date applies only to the specific sources checked on .
  • ● rows do not assert a state threshold. Thirty-two rows correctly identify the NPDES issuer and official starting page but should not be read as confirming a specific disturbance threshold for that state.
  • Parcel conditions control. Wetlands, streams, floodplains, protected species, conservation easements, timber classification, and common-plan status can change the result on a given property regardless of total cleared area.
  • Local rules are listed only as a check category, not verified at the municipal level except where the source directly states a local threshold.
  • Stated thresholds contain conditions. Exemptions, delegated programs, project-type pathways, and site-specific conditions all apply within each threshold statement. The threshold is a starting point, not a yes/no answer.
  • This is not a property-specific legal determination or environmental assessment. Consult the responsible issuing agencies and, where warranted, a qualified environmental professional before undertaking land disturbance.

How should this page be cited?

How to cite this page

Ocala Land Clearing Research. "Land Clearing Permit Requirements by State: 2026 Reference." Dataset version 1.0.0. Published and last verified .

https://ocalalandclearing.net/resources/land-clearing-permit-requirements-by-state/

  • Organization: Ocala Land Clearing Research
  • Page title: Land Clearing Permit Requirements by State: 2026 Reference
  • Dataset version: 1.0.0
  • Published:
  • Last verified:
  • Canonical URL: https://ocalalandclearing.net/resources/land-clearing-permit-requirements-by-state/
  • Access date: Supply the date accessed

Where can the permit requirements dataset be downloaded?

Version 1.0.0 contains 51 jurisdiction rows and a separate 27-source ledger. Files are served without registration, email capture, redirect tracking, or a JavaScript requirement. Dated filenames are fixed to this version; stable aliases resolve to the most recently verified release.

Dataset fields

jurisdiction, postal_code, verification_tier, npdes_authority_type, npdes_or_program_authority, official_program_page_url, national_baseline_to_check, verified_state_rule_or_overlay, other_permit_screens, local_detail, verified_on, primary_source_title, primary_source_url, secondary_source_title, secondary_source_url, local_source_urls, publication_status, method_note.

File integrity

SHA-256 checksums — version 1.0.0 / 2026-07-23
FileSHA-256
land-clearing-permit-requirements-by-state-2026-07-23.csvbf28d9d664c6f22f91d5bb973aaa13142da9e27f48f01f7c497df05d4aa6a0cf
land-clearing-permit-requirements-by-state-2026-07-23.json4314bdb8b61bd597341b53606601880ef161e8dc17edb4eb390330adf364283f

What else do readers ask about land clearing permits by state?

Does land clearing always require a permit?

Not automatically. The federal construction stormwater baseline covers land disturbance of one acre or more (or a smaller site in a larger common plan totaling one acre or more). Below that threshold, state erosion and sediment control programs, local grading and tree-removal ordinances, wetland and waterway rules, forest-practice notifications, and burn regulations can independently require permits or approvals — sometimes at much smaller disturbance areas than one acre.

What is the one-acre federal construction stormwater threshold?

EPA's Construction General Permit covers stormwater discharges from construction sites disturbing one acre or more, and smaller sites that are part of a larger common plan of development or sale that will ultimately disturb one acre or more. Most states run their own authorized NPDES programs and issue the construction permit; four jurisdictions (Massachusetts, New Hampshire, New Mexico, and the District of Columbia) have EPA issue the NPDES permit directly.

What is a common plan of development or sale?

A common plan of development or sale is a contiguous area where multiple separate, smaller construction activities may be taking place at different times but under one plan. If the total planned disturbance for that common area reaches one acre or more, each individual site within it — even if it disturbs less than one acre on its own — can be subject to the construction stormwater permit requirement.

What do the ★ and ● verification tiers mean?

★ (star) means the summarized state-specific rule or official program page was read directly against a primary government source and is verified as of July 23, 2026. ● (bullet) means the NPDES authority and official program starting point were compiled from U.S. EPA primary sources, but the current state-specific construction permit has not received a full row-level re-verification for dataset version 1.0. Rows marked ● correctly identify the NPDES issuer and official starting page but do not assert a specific state threshold.

Which states have EPA issue the construction stormwater permit?

Four jurisdictions in this dataset have EPA (not the state) issue NPDES permits: Massachusetts (EPA Region 1), New Hampshire (EPA Region 1), New Mexico (EPA Region 6), and the District of Columbia (EPA Region 3). New Hampshire also has a state Alteration of Terrain program that operates separately from NPDES.

Does clearing less than one acre mean no permit is needed?

No. The one-acre federal baseline is not a universal permission to clear without a permit below that threshold. Multiple independently triggered requirements can apply at much smaller disturbance areas: Maryland requires an erosion and sediment control plan at 5,000 square feet; Pennsylvania and Delaware both have 5,000-square-foot triggers; Virginia local programs generally apply at 10,000 square feet; New Hampshire's Alteration of Terrain program can apply at 100,000 square feet cumulative. Local grading, tree-removal, wetlands, waterway, and burn rules operate entirely separately.

What other permits apply besides the construction stormwater permit?

Land clearing can trigger several independent permit layers: (1) local grading or land-disturbance ordinances, (2) local tree-removal or canopy ordinances, (3) federal or state wetlands permits (Section 404 of the Clean Water Act and state equivalents), (4) state forest-practice notifications or permits for timber operations, (5) debris-burning authorization, and (6) protected-species, conservation-easement, or floodplain rules. Each applies independently of the stormwater permit.

What is an erosion and sediment control plan?

An erosion and sediment control plan (also called an E&SC plan or SESC plan) is a written document specifying the best management practices to prevent soil erosion and off-site transport of sediment during land-disturbing activities. Many states require an approved plan before disturbance begins; the specific content, review authority, and approval process vary by state and sometimes by county.

Can local ordinances be stricter than the state threshold?

Yes. State rules set a floor; local governments can adopt stricter requirements. Virginia is an example where the state establishes a general 10,000-square-foot threshold for local programs, but localities in Chesapeake Bay Preservation Areas apply a 2,500-square-foot threshold. Local tree-removal and grading ordinances routinely apply at much smaller disturbance areas than any state or federal stormwater threshold.

Why does Florida have both a state stormwater CGP and a federal Section 404 requirement?

These are two independent regulatory programs. Florida's CGP covers stormwater discharges from disturbed land to state surface waters or MS4s. Section 404 covers discharges of dredged or fill material into waters of the United States, including wetlands. As of July 23, 2026, Florida DEP's State 404 program remains paused, so the U.S. Army Corps of Engineers is the current Section 404 permitting authority in Florida. Both permits may be needed for the same project.


What are the source documents?

All sources were read directly on .

Federal baseline sources (all jurisdictions)

  1. U.S. Environmental Protection Agency, NPDES State Program Authority. epa.gov/npdes/npdes-state-program-authority
  2. U.S. Environmental Protection Agency, NPDES Permits around the Nation. epa.gov/npdes-permits
  3. U.S. Environmental Protection Agency, Construction General Permit (CGP) Frequent Questions. epa.gov/npdes/construction-general-permit-cgp-frequent-questions

State-specific primary sources (★ rows)

  1. Alabama Department of Environmental Management, Do I Need Permit Coverage? adem.alabama.gov — Do I Need Permit Coverage?
  2. Alaska Division of Mining, Land and Water, Alaska Forest Resources and Practices Regulations (11 AAC 95.030). dnr.alaska.gov — 11 AAC 95.030
  3. Arkansas Division of Environmental Quality, General Stormwater Permits. adeq.state.ar.us — General Stormwater Permits
  4. CAL FIRE, California Department of Forestry and Fire Protection, CalTREES. fire.ca.gov — CalTREES
  5. Delaware General Assembly, Delaware Code, Title 7, Chapter 40 — Erosion and Sedimentation Control. delcode.delaware.gov/title7/c040/
  6. Delaware DNREC, FY2026 CWA Section 319 Grant Guidance. FY26-CWA-Section-319-Grant-RFP.pdf
  7. District of Columbia Office of Documents and Administrative Issuances, 21 DCMR Chapter 5 — Stormwater Management. 21 DCMR Chapter 5 (November 14, 2025)
  8. Florida Department of Environmental Protection, Construction Activity. floridadep.gov — Construction Activity
  9. U.S. Army Corps of Engineers, South Atlantic Division, Florida Regulatory Program. sad.usace.army.mil — Florida Regulatory
  10. Marion County, Florida, Planning and Zoning Fees and Forms. marionfl.org — P&Z Fees and Forms
  11. Marion County, Florida, Right-of-Way Permitting. marionfl.org — Right-of-Way Permitting
  12. Marion County Fire Rescue, Florida, Burn Permits. marionfl.org — Burn Permits
  13. Kentucky Division of Water, KYR10 Permit Page. KYR10PermitPage.pdf
  14. Maryland Department of the Environment, Soil Erosion and Sediment Control. mde.maryland.gov — Erosion and Sediment Control
  15. Michigan EGLE, SESC Training Manual, Units 1 through 5. michigan.gov — SESC Training Manual
  16. New Hampshire Department of Environmental Services, Alteration of Terrain. des.nh.gov — Alteration of Terrain
  17. New Jersey Department of Agriculture, Soil Erosion and Sediment Control Program. nj.gov/agriculture — Soil Erosion Program
  18. New Jersey Legislature, Soil Erosion and Sediment Control Act (Chapter 251). nj.gov/agriculture — Chapter 251
  19. North Carolina Department of Environmental Quality, Erosion and Sediment Control FAQs. deq.nc.gov — E&SC FAQs
  20. Oregon Department of Forestry, E-Notification. oregon.gov/odf — E-Notification
  21. Pennsylvania Department of Environmental Protection, Pennsylvania Code, 25 Pa. Code §102.4 — Erosion and Sediment Control Requirements. 025_0102.pdf
  22. Rhode Island Department of Environmental Management, Stormwater Construction Permitting. dem.ri.gov — Stormwater Construction Permitting
  23. South Carolina Department of Environmental Services, Less Than 1 Acre of Land Disturbance. des.sc.gov — Less Than 1 Acre
  24. South Carolina Department of Environmental Services, 2026 CGP Formal Response to Comments. FormalResponsetoComments_2026NPDESCGP.pdf
  25. Virginia General Assembly, Code of Virginia — Virginia Erosion and Stormwater Management Act. law.lis.virginia.gov — VESMA Act
  26. Washington Department of Natural Resources, Forest Practices Application. dnr.wa.gov — Forest Practices Application